组织在两个互斥项目中选择:A 的 IRR 更高但 NPV 更低,B 的 IRR 更低但 NPV 更高。哪个更值得投,为什么?
An organisation is choosing between two mutually exclusive projects. Project A has a higher IRR but lower NPV. Project B has a lower IRR but higher NPV. Which is the better investment and why?
选项
- A.Project A: higher IRR always indicates a better investment.
- B.Project B, for mutually exclusive projects, NPV is generally the preferred decision criterion because it measures the absolute dollar value added to the organisation, not just the return rate on the investment.
- C.Project A: faster return on investment is always preferable.
- D.Both provide equal value: select based on risk profile.
解析
解析:B 正确。对互斥项目,NPV 是首选指标,因为它最大化绝对的价值创造。当项目规模差异较大时,IRR 会产生误导(高 IRR 的小项目总价值可能低于低 IRR 的大项目)。这是公司金融中确立的原则:互斥项目上 NPV 与 IRR 冲突时,以 NPV 为准。IRR(A、C)适合用门槛率筛选独立项目,不适合比较规模不同的互斥方案。
Rationale:B is correct. For mutually exclusive projects, NPV is the preferred metric: it maximises absolute value creation. IRR can be misleading when project sizes differ significantly (a high-IRR small project may create less total value than a lower-IRR large project). This is a well-established principle in corporate finance: when NPV and IRR conflict for mutually exclusive projects, choose by NPV. IRR (A, C) is useful for ranking independent projects against a hurdle rate but not for comparing exclusive alternatives of different scales.