财务指标与投资决策 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-317

题目

项目经理被要求评估两个项目的优先级。项目 A 的净现值(NPV)为 50 万美元,项目 B 为 35 万美元,两者工期与资源需求相同。应优先选择哪个?
A project manager is asked to evaluate two projects for prioritisation. Project A has an NPV of $500,000 and Project B has an NPV of $350,000. Both have the same duration and resource requirements. Which should be prioritised?

选项

  1. A.Project B: a lower NPV suggests lower risk.
  2. B.Project A, a higher NPV indicates greater financial value to the organisation.
  3. C.Both should be run simultaneously to maximise total NPV.
  4. D.Neither: NPV alone is insufficient to make a prioritisation decision.
正确答案:B

解析

解析:B 正确。净现值(NPV)以现值口径衡量项目为组织增加的财务价值,NPV 越高财务收益越大。在其他条件相同时(工期、资源一致),应优先 NPV 更高的项目。NPV 不反映风险高低(A);同时开展与资源需求相同的假设矛盾(C);题干已明确其他条件相同,因此仅凭 NPV 即可比较(D 不成立)。 Rationale:B is correct. Net Present Value (NPV) represents the financial value a project adds to the organisation in today's money. A higher NPV means greater financial benefit. When all other factors are equal (same duration, same resources), the project with the higher NPV should be prioritised. NPV does not indicate risk level (A). Running both simultaneously contradicts the assumption of equal resource requirements (C). The question explicitly provides equal conditions for comparison (D is incorrect here).

同考点练习题