你的项目是多个争夺有限组织资金的项目之一。为保住其优先级,最有效的论据是什么?
Your project is one of several competing for limited organisational funding. To protect its priority, the most effective argument is:
选项
- A.How much work the team has already done.
- B.How the project aligns with strategy and the value it is expected to deliver.
- C.How hard the team is working on it.
- D.How long the project has been running.
解析
解析:项目组合的资金决策依据是战略对齐与预期价值。已投入的成本不是前瞻性理由;努力程度和运行时长也不能说明价值。
Rationale:Portfolio funding decisions rest on strategic alignment and expected value. Sunk effort is not a forward-looking justification; effort and duration say nothing about worth.