题目
某项目的效益成本比(BCR)为 2.5,说明什么?
A project has a Benefit-Cost Ratio (BCR) of 2.5. What does this indicate?
选项
- A.For every $1 invested, the project generates $2.50 in benefits
- B.The project exceeds its budget by 2.5 times
- C.The project will take 2.5 years to complete
- D.The project has a 2.5% risk of failure
解析
解析:BCR 大于 1.0 表示项目效益超过成本。
Rationale:A BCR greater than 1.0 indicates that the benefits exceed the project costs.
同考点练习题
-
PMP202611-071 · 答案 B
-
PMP202611-135 · 答案 B
-
PMP202611-212 · 答案 B
-
PMP202611-317 · 答案 B
-
PMP202611-318 · 答案 D
-
PMP202611-409 · 答案 B
-
PMP202611-411 · 答案 A
-
PMP202611-417 · 答案 B