成本管理 中等 Process 过程域 题号 PMP202611-076

题目

某项目的效益成本比(BCR)为 2.5,说明什么?
A project has a Benefit-Cost Ratio (BCR) of 2.5. What does this indicate?

选项

  1. A.For every $1 invested, the project generates $2.50 in benefits
  2. B.The project exceeds its budget by 2.5 times
  3. C.The project will take 2.5 years to complete
  4. D.The project has a 2.5% risk of failure
正确答案:A

解析

解析:BCR 大于 1.0 表示项目效益超过成本。 Rationale:A BCR greater than 1.0 indicates that the benefits exceed the project costs.