商业价值与价值交付 · PMP 练习题解析

商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-412

题目

项目依据“节省 100 万美元”的商业论证获批。执行到中途,新分析显示实际只能节省 40 万美元,而项目成本为 60 万美元。项目经理应该怎么做?
A project was approved based on a business case that projected $1M in cost savings. Midway through the project, new analysis shows the savings will be only $400,000. The project cost is $600,000. What should the project manager do?

选项

  1. A.Reduce project costs to $400,000 or less to restore the break-even point.
  2. B.Wait until project completion to report, the analysis may change again.
  3. C.Report the revised business case analysis to the sponsor and governance body immediately, with a clear recommendation that the project no longer justifies its cost. Recommend cancellation or scope reduction and allow decision-makers to decide.
  4. D.Continue the project: the $400,000 savings still exceeds zero.
正确答案:C

解析

解析:C 正确。花 60 万只换来 40 万节省,投资回报为负。项目经理有义务立即向治理层报告商业论证的变化——沉没成本谬误不能成为继续一个毁损价值项目的理由。这正是 Business Environment 领域的核心能力:持续验证项目是否配得上其投入。不管不顾地继续(D)无视负回报;强行压成本(A)未必可行;拖延上报(B)剥夺了决策者的关键信息。 Rationale:C is correct. A project that costs $600,000 to deliver $400,000 in savings has a negative ROI. The PM has an obligation to report this business case change to governance immediately, the sunk cost fallacy cannot justify continuing a value-destroying project. This is a core Business Environment competency: continuously validating that projects justify their investment. Continuing regardless (D) ignores the negative ROI. Forced cost reduction (A) may not be feasible. Delaying reporting (B) deprives decision-makers of critical information.

同考点练习题