整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-408

题目

项目经理收到变更请求:范围增加 20%,但预算与工期不变。提交 CCB 前最重要的分析是什么?
A project manager receives a change request that would increase project scope by 20% with no change to budget or timeline. What is the most important analysis to perform before presenting this to the CCB?

选项

  1. A.Whether the change aligns with the project's business case.
  2. B.A comprehensive impact analysis showing the realistic effect on schedule, cost, quality and risk: to inform the CCB that the "no change to budget or timeline" assumption is likely incorrect, and present options for achieving the additional scope.
  3. C.Whether the requestor has authority to submit a change request.
  4. D.Whether the team has capacity to absorb the additional scope.
正确答案:B

解析

解析:B 正确。范围增 20% 而预算工期不变,几乎肯定不现实。提交 CCB 前,项目经理最重要的职责是做严谨的影响分析,把真实约束摆清楚;带着未经纠正的不现实假设上会,等于误导 CCB。必须说明实现新增范围实际需要什么,并给出选项。商业论证契合(A)相关但次于影响分析;团队产能(D)只是分析的一部分,视野不够全。 Rationale:B is correct. A 20% scope increase with no change to budget or timeline is almost certainly unrealistic. The PM's most important role before the CCB is to perform a rigorous impact analysis that demonstrates the actual constraints. Presenting a change request that contains unrealistic assumptions without correction would mislead the CCB. The PM must show what achieving the additional scope actually requires, and present options. Business case alignment (A) is relevant but secondary to impact analysis. Team capacity (D) is part of the analysis but not the most comprehensive view.

同考点练习题