产品已开发 8 个冲刺后,产品负责人想衡量已交付功能是否真的被使用。这属于什么实践?
A product has been in development for 8 sprints. The Product Owner now wants to measure whether the delivered features are actually being used. What practice does this represent?
选项
- A.Sprint review: checking feature completion.
- B.Velocity tracking: measuring story point throughput.
- C.Outcome-based measurement and validated learning: using product analytics and user behaviour data to determine whether delivered features create real value, enabling evidence-based backlog prioritisation.
- D.Definition of Done: verifying features meet acceptance criteria.
解析
解析:C 正确。交付后衡量功能的真实使用情况,属于精益创业与成果导向的敏捷实践,即验证交付是否带来预期的用户行为(验证式学习)。它回答的是“我们做对了东西吗”,而不是“我们把东西做对了吗”。冲刺评审(A)展示可运行软件但不衡量真实使用;完成定义(D)保证技术质量;速率(B)衡量吞吐。只有成果度量把交付与真实价值实现连起来。
Rationale:C is correct. Measuring actual feature usage after delivery is a Lean Startup and outcome-based agile practice: checking whether delivered features create the intended user behaviour (validated learning). It answers "did we build the right thing?" rather than "did we build the thing right?" Sprint review (A) shows working software but doesn't measure real-world usage. DoD (D) ensures technical quality. Velocity (B) measures throughput. Outcome-based measurement is the practice that connects delivery to actual value realisation.