题目
某 Scrum 团队刚完成第 10 个冲刺。速率数据:第 1~3 冲刺平均 15 点,第 4~7 平均 28 点,第 8~10 平均 32 点。未来冲刺计划应采用哪个速率?
A Scrum team has just completed its 10th sprint. Looking at their velocity data: sprints 1–3 averaged 15 points, sprints 4–7 averaged 28 points, sprints 8–10 averaged 32 points. What velocity should be used for future sprint planning?
选项
- A.28 points: use the middle cluster which is the most representative.
- B.32 points, use the most recent stable velocity which reflects current team capability after the initial ramp-up period.
- C.25 points: average across all 10 sprints.
- D.35 points: project a growth trend since velocity has been increasing.
解析
解析:B 正确。团队明显经历过爬坡(前 3 个冲刺属形成期),早期数据不能代表当前能力。只取最近稳定速率(第 8~10 冲刺的 32 点)对未来预测最准。总平均(C)把爬坡期算进去,压低了估算;继续外推增长(D)假设趋势未触顶,风险大;中间区间(A)优于总平均,但仍无谓地掺入了爬坡数据。
Rationale:B is correct. When a team has clearly ramped up (sprints 1–3 were early formation), the early data is unrepresentative of current capability. Using only the most recent stable velocity (32 from sprints 8–10) gives the most accurate forecast for future sprints. The overall average (C) includes the ramp-up period which depresses the estimate. Projecting further growth (D) extrapolates a trend that may have plateaued. The middle cluster (A) is better than the overall average but still includes ramp-up data unnecessarily.