题目
某敏捷团队完成冲刺,但因多个冲刺累积的技术债未清,增量不具备可发布性。最重要的纠正措施是什么?
An agile team finishes a sprint and the increment is not potentially shippable due to unresolved technical debt accumulated over several sprints. What is the most important corrective action?
选项
- A.Schedule a hardening sprint to clean up all technical debt before continuing feature delivery.
- B.Allocate a portion of each future sprint's capacity to addressing technical debt alongside feature delivery: preventing accumulation rather than batching cleanup, and update the Definition of Done to prevent future debt.
- C.Accept the technical debt and continue feature delivery, the team will address it at end of the project.
- D.Reduce sprint velocity targets to allow more time for quality work.
解析
解析:B 正确。技术债管理应持续进行而非批量偿还:每个冲刺划出 20%~30% 产能与功能并行还债,才是可持续做法;更新完成定义可防止新债产生。“加固冲刺”(A)是敏捷反模式,说明团队没有持续维持质量;拖到项目末期(C)会让债务演变成无法收拾的危机;单纯下调速率目标(D)并未直接解决质量问题。
Rationale:B is correct. Technical debt management should be continuous, not batched. Allocating 20–30% of sprint capacity to debt reduction alongside feature delivery is the sustainable practice. Updating the DoD prevents future debt creation. Hardening sprints (A) are an agile anti-pattern. They indicate the team isn't maintaining quality continuously. Deferring to end-of-project (C) turns debt into an unmanageable crisis. Reducing velocity targets (D) doesn't address the quality problem directly.