题目
项目团队被告知项目将在 1 个月后取消,士气崩塌、产能明显下降。项目经理应优先做什么?
A project team has been informed that their project will be cancelled in one month. Team morale has collapsed and productivity has dropped significantly. What should the project manager prioritise?
选项
- A.Acknowledge the team's feelings openly, help team members transition to new roles, ensure knowledge is documented before departure, and deliver the most valuable work remaining in the time available.
- B.Focus solely on completing as many deliverables as possible before cancellation.
- C.Allow team members to disengage since the project is being cancelled anyway.
- D.Issue performance warnings to team members whose productivity has declined.
解析
解析:A 正确。项目取消时,项目经理的责任既包括任务层面的收尾(文档、知识转移、交付收口),也包括人的层面的领导(承认情绪现实、支持转岗、维护尊严)。被妥善对待的团队在收尾期仍能保持产出,并把对组织的正面印象带出去。只看交付数量(B)反而会压低收尾所需产能;放任脱离(C)是放弃收尾责任;此时发绩效警告(D)完全不合时宜。
Rationale:A is correct. When a project is cancelled, the PM's responsibilities include both task-level closure (documentation, knowledge transfer, deliverable completion) and human-level leadership (acknowledging the emotional reality, supporting transitions, maintaining dignity). Teams that feel supported through cancellation remain productive and carry positive perceptions of the organisation forward. Ignoring the human dimension (B) reduces the productivity needed for closure. Allowing disengagement (C) abandons closure responsibility. Performance warnings (D) are tone-deaf in the context of a cancellation.