题目
冲刺计划时,一名成员说“我不知道怎么实现这个故事——我从没做过”,其他成员也不熟悉。恰当的敏捷应对是什么?
During sprint planning, a team member says "I don't know how to implement this story: I've never done it before." Other team members are also unfamiliar. What is the appropriate agile response?
选项
- A.Remove the story from the sprint: unknown work cannot be committed to.
- B.Ask the most experienced developer to take sole responsibility for the story.
- C.Create a time-boxed spike (research task) in the sprint to investigate the unknown, size it appropriately, and plan the actual implementation story for a future sprint once the approach is understood.
- D.Commit to the story anyway and figure it out during implementation.
解析
解析:C 正确。“探针”(spike)是敏捷处理技术未知的工具:限时调研、产出的是知识而非生产代码,从而让团队能正确估算并规划真正的实现。这正是面对“我们还不知道怎么干”的标准应对。直接移除故事(A)可能不必要地推迟重要工作;无知就承诺(D)制造冲刺风险;交给一个人(B)集中风险且不积累团队知识。
Rationale:C is correct. A "spike" is the agile tool for handling technical unknowns. It is a time-boxed investigation that produces knowledge (not production code): enabling the team to estimate and plan the actual implementation properly. This is the standard agile response to "we don't know how to do this yet." Removing the story entirely (A) may delay important work unnecessarily. Committing without knowledge (D) creates sprint risk. Assigning to one person (B) concentrates risk without building team knowledge.