管理相关方参与 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-375

题目

某敏捷团队的冲刺评审每次只有产品负责人到场,其他业务相关方都不参加。最可能的后果是什么,应该怎么做?
An agile team's sprint review consistently attracts only the Product Owner: no other business stakeholders attend. What is the most likely consequence and what should be done?

选项

  1. A.The team misses diverse feedback that could improve the product. The Scrum Master and PO should actively engage key stakeholders to attend sprint reviews by making them short, valuable and accessible, and by demonstrating what they miss when absent.
  2. B.Cancel sprint reviews and replace them with written summaries sent to stakeholders.
  3. C.Make sprint review attendance mandatory for all stakeholders.
  4. D.No consequence: the PO represents all stakeholders adequately.
正确答案:A

解析

解析:A 正确。冲刺评审的意义在于汇集广泛的相关方反馈,产品负责人再能干也无法完全替代多元视角。出席率低通常意味着相关方不认为参会值得。让评审更有价值、更短、与业务决策直接挂钩,才能提升自愿参与。产品负责人代表所有人(D)在复杂产品上不成立;取消评审(B)等于废掉关键的检视—调整机制;强制出席(C)只有服从而无投入。 Rationale:A is correct. Sprint review exists to gather broad feedback from stakeholders, the PO alone, however capable, cannot fully substitute for diverse stakeholder perspectives. Low attendance usually means stakeholders don't perceive value in attending. Making reviews more compelling, shorter and explicitly connected to business decisions increases voluntary participation. The PO representing all stakeholders (D) is insufficient for complex products. Cancelling reviews (B) removes the key inspect-and-adapt mechanism. Mandatory attendance (C) creates compliance without engagement.