团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-376

题目

项目经理为高技术项目组建团队,可在“经验丰富的通才团队”与“专业深厚但协作经验有限的专家团队”之间选择。应以哪些因素作为决策依据?
A project manager is building a team for a highly technical project. She can choose between an experienced generalist team or a specialist team with deep expertise but limited collaboration experience. What factors should guide the decision?

选项

  1. A.Evaluate the project's specific technical depth requirements versus collaboration and communication needs, then consider a hybrid composition or plan for team development to address whichever gap exists.
  2. B.Choose based on cost: specialists typically charge more so generalists are usually better value.
  3. C.Always choose specialists: technical projects require deep expertise above all else.
  4. D.Always choose generalists: collaboration experience produces better outcomes.
正确答案:A

解析

解析:A 正确。资源获取决策应由项目具体需求分析驱动。技术性强但定义清晰的问题可能需要专家深度;复杂、跨职能的问题需要协作能力。深思熟虑的混合组队或针对缺口的发展计划通常是最佳答案。“总是专家”(C)与“总是通才”(D)都不合情境。成本(B)是因素之一,但不应成为高技术项目的首要决策依据。 Rationale:A is correct. Resource acquisition decisions should be driven by project-specific needs analysis. Highly technical but well-defined problems may need specialist depth; complex, cross-functional problems need collaboration capability. A thoughtful hybrid or a development plan for the gap is often the best answer. Neither "always specialists" (C) nor "always generalists" (D) is contextually appropriate. Cost (B) is a factor but should not be the primary decision driver for highly technical projects.