题目
项目经理为高技术项目组建团队,可在“经验丰富的通才团队”与“专业深厚但协作经验有限的专家团队”之间选择。应以哪些因素作为决策依据?
A project manager is building a team for a highly technical project. She can choose between an experienced generalist team or a specialist team with deep expertise but limited collaboration experience. What factors should guide the decision?
选项
- A.Evaluate the project's specific technical depth requirements versus collaboration and communication needs, then consider a hybrid composition or plan for team development to address whichever gap exists.
- B.Choose based on cost: specialists typically charge more so generalists are usually better value.
- C.Always choose specialists: technical projects require deep expertise above all else.
- D.Always choose generalists: collaboration experience produces better outcomes.
解析
解析:A 正确。资源获取决策应由项目具体需求分析驱动。技术性强但定义清晰的问题可能需要专家深度;复杂、跨职能的问题需要协作能力。深思熟虑的混合组队或针对缺口的发展计划通常是最佳答案。“总是专家”(C)与“总是通才”(D)都不合情境。成本(B)是因素之一,但不应成为高技术项目的首要决策依据。
Rationale:A is correct. Resource acquisition decisions should be driven by project-specific needs analysis. Highly technical but well-defined problems may need specialist depth; complex, cross-functional problems need collaboration capability. A thoughtful hybrid or a development plan for the gap is often the best answer. Neither "always specialists" (C) nor "always generalists" (D) is contextually appropriate. Cost (B) is a factor but should not be the primary decision driver for highly technical projects.
同考点练习题
-
PMP202611-029 · 答案 C
-
PMP202611-037 · 答案 C
-
PMP202611-136 · 答案 A
-
PMP202611-149 · 答案 B
-
PMP202611-160 · 答案 B
-
PMP202611-161 · 答案 B
-
PMP202611-222 · 答案 B
-
PMP202611-251 · 答案 B