效益实现与价值管理 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-369

题目

项目经理向指导委员会汇报效益实现计划,其中关键效益要到交付后 18 个月才可衡量。有委员质疑是否合理。项目经理应如何解释?
A project manager is presenting the project's benefits realisation plan to the steering committee. The plan shows that key benefits will only be measurable 18 months after project delivery. A steering committee member questions whether this is appropriate. What should the project manager explain?

选项

  1. A.Benefits realisation measurement timelines vary by benefit type: some outcomes (behaviour change, capability building, market penetration) naturally take months or years to manifest. The plan should define leading indicators measurable sooner that predict whether lagging outcomes are on track.
  2. B.Shorten the measurement window to 6 months to satisfy the committee's concern.
  3. C.The 18-month measurement window is too long: benefits should be measurable immediately after delivery.
  4. D.Benefits realisation is operations' responsibility, the project team should not be accountable for post-delivery outcomes.
正确答案:A

解析

解析:A 正确。效益实现的周期由效益本身的性质决定,而非委员会偏好。复杂的组织级成果确实需要 12~24 个月才可衡量。正确做法是定义领先指标(早期信号),用以确认项目正在通往滞后成果。强行压到 6 个月(B)只会产出无意义的测量。效益实现是组织层面的责任(项目经理通过项目共同承担),并非只由运营负责(D)。 Rationale:A is correct. Benefits realisation timelines are determined by the nature of the benefit, not by committee preference. Complex organisational outcomes legitimately take 12–24 months to be measurable. The correct response is to define leading indicators (early signals) that confirm the project is on track to deliver lagging outcomes. Forcing an artificial 6-month window (B) produces meaningless measurements. Benefits realisation is the organisation's responsibility (shared by the PM through the project), not exclusively operations (D).