题目
项目经理管理横跨四国的虚拟团队。某国成员经常不预警就错过截止日期。调查后发现,他们不愿向权威人物提出问题。根因是什么,最佳应对是什么?
A project manager is managing a virtual team across four countries. Team members from one country consistently miss deadlines without prior warning. Upon investigation, the project manager learns they do not feel comfortable raising issues to authority figures. What is the root cause and best response?
选项
- A.Issue a formal warning to the team members for missed deadlines.
- B.Replace the team members with local resources who are more comfortable with direct communication.
- C.Increase check-in frequency to catch missed deadlines earlier.
- D.The root cause is a cultural high-power-distance dynamic. Adapt the communication approach by creating low-barrier escalation channels (anonymous reporting, peer relays) and explicitly normalising the expectation that raising issues is welcomed and expected.
解析
解析:D 正确。高权力距离文化会抑制下属向权威提出问题,这是有充分研究支撑的跨文化现象。项目经理应调整管理方式,而不是惩罚由文化驱动的行为。建立安全的上报渠道、并明确示范“提问题是受重视的”,正对根因。正式警告(A)只是惩罚文化行为而不解决问题;换人(B)过度;加密检查(C)只能抓到症状,无法让团队主动发声。
Rationale:D is correct. High-power-distance cultures discourage subordinates from raising problems to authority figures, a well-documented cross-cultural dynamic. The PM must adapt their management approach rather than punishing culturally-driven behaviour. Creating safe escalation channels and explicitly modelling that raising issues is valued addresses the root cause. Formal warnings (A) punish a cultural behaviour without fixing it. Replacing team members (B) is disproportionate. More check-ins (C) catches symptoms but doesn't empower the team to speak up proactively.