商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-368

题目

组织按战略契合度与财务回报选择项目。两个项目 NPV 相同:X 支撑核心战略目标,Y 支撑非战略性的部门目标。应优先哪个?
An organisation selects projects based on strategic alignment and financial return. Two projects have equal NPV. Project X supports a core strategic objective; Project Y supports a non-strategic department goal. Which should be prioritised?

选项

  1. A.Run both simultaneously since they have equal financial returns.
  2. B.Neither: conduct a more detailed analysis before selecting either.
  3. C.Project X, when financial returns are equal, strategic alignment is the tiebreaker for portfolio prioritisation.
  4. D.Project Y: non-strategic departments need investment too.
正确答案:C

解析

解析:C 正确。项目组合管理采用多准则评估。NPV 相同时,战略契合度成为决胜项:核心战略项目推动组织根本方向,通常还带来超出自身 NPV 的乘数效应。同时开展(A)隐含资源无限的假设;部门公平(D)不是组合管理的准则;信息已足以决策时再做详细分析(B)并无必要。 Rationale:C is correct. Portfolio management uses multiple criteria. When NPV is equal, strategic alignment becomes the tiebreaker: core strategic projects advance the organisation's fundamental direction and typically have multiplicative benefits beyond their own NPV. Running both simultaneously (A) assumes unlimited resources. Departmental equity (D) is not a portfolio management criterion. Further analysis (B) is unnecessary when sufficient information is already available to decide.