题目
项目经理正在实施整体变更控制。有人提交了一份通过缩减范围来省成本的变更请求。谁有权批准该变更?
A project manager is performing Perform Integrated Change Control. A change request has been submitted that would reduce project scope to save cost. Who has the authority to approve this change?
选项
- A.The project manager: they are responsible for scope management.
- B.The team member who submitted the change request.
- C.The Change Control Board (CCB) or the governance body designated in the project management plan to approve changes.
- D.The project sponsor alone, since scope reductions affect the business case.
解析
解析:C 正确。变更批准权限由项目管理计划界定,通常归变更控制委员会(CCB)。CCB 的成员构成与升级阈值在规划阶段确定。项目经理负责处理与推动变更,但对范围变更没有单方批准权(A);提出者(B)不能批准自己的变更;仅发起人(D)是否为指定批准方取决于项目管理计划的规定。
Rationale:C is correct. Change approval authority is defined in the project management plan and typically resides with the Change Control Board (CCB). The CCB membership and escalation thresholds are established during planning. The project manager processes and facilitates changes but does not have unilateral approval authority for scope changes (A). The requestor (B) cannot approve their own change. The sponsor alone (D) may or may not be the designated approval authority. It depends on what the project management plan specifies.
同考点练习题
-
PMP202611-006 · 答案 B
-
PMP202611-031 · 答案 C
-
PMP202611-056 · 答案 C
-
PMP202611-066 · 答案 B
-
PMP202611-093 · 答案 D
-
PMP202611-116 · 答案 B
-
PMP202611-125 · 答案 B
-
PMP202611-191 · 答案 B