题目
某 Scrum 团队的冲刺燃尽图在前 5 天(共 10 天冲刺)呈水平直线。这说明什么,应采取什么行动?
A Scrum team's sprint burn-down chart shows a flat line for the first 5 days of a 10-day sprint. What does this indicate and what action is appropriate?
选项
- A.The team is updating the burn-down incorrectly: coaching on the tool is needed.
- B.The team needs to work overtime in the second half to recover.
- C.The flat line indicates no work is being completed, the Scrum Master should identify blockers immediately and facilitate their removal to prevent sprint failure.
- D.The team is on track: some work takes longer before showing progress.
解析
解析:C 正确。10 天冲刺里 5 天燃尽图完全持平是严重警报:要么确实没有任何工作完成(存在重大障碍),要么看板/图表没更新。Scrum Master 必须立刻查明并采取行动。每日站会本应暴露障碍,而冲刺过半仍呈直线,要求促进者紧急介入。把直线当作正常(D)无视了明确的求救信号;只顾图表更新(A)次于核实真实完成情况;未查明原因就加班(B)违反可持续节奏。
Rationale:C is correct. A flat burn-down for 5 of 10 sprint days is a critical warning signal: either no work is completing (serious blocker) or the board/chart is not being updated. The Scrum Master must investigate and act immediately. The daily standup should surface blockers, but a flat line visible at mid-sprint demands urgent facilitator action. Normalising it (D) ignores a clear distress signal. Chart updating (A) is secondary to checking actual work completion. Overtime (B) violates sustainable pace without understanding the cause.