看板与流动管理 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-338

题目

某 Scrum 团队的冲刺燃尽图在前 5 天(共 10 天冲刺)呈水平直线。这说明什么,应采取什么行动?
A Scrum team's sprint burn-down chart shows a flat line for the first 5 days of a 10-day sprint. What does this indicate and what action is appropriate?
某 Scrum 团队的冲刺燃尽图在前 5 天(共 10 天冲刺)呈水平直线。这说明什么,应采取什么行动?

选项

  1. A.The team is updating the burn-down incorrectly: coaching on the tool is needed.
  2. B.The team needs to work overtime in the second half to recover.
  3. C.The flat line indicates no work is being completed, the Scrum Master should identify blockers immediately and facilitate their removal to prevent sprint failure.
  4. D.The team is on track: some work takes longer before showing progress.
正确答案:C

解析

解析:C 正确。10 天冲刺里 5 天燃尽图完全持平是严重警报:要么确实没有任何工作完成(存在重大障碍),要么看板/图表没更新。Scrum Master 必须立刻查明并采取行动。每日站会本应暴露障碍,而冲刺过半仍呈直线,要求促进者紧急介入。把直线当作正常(D)无视了明确的求救信号;只顾图表更新(A)次于核实真实完成情况;未查明原因就加班(B)违反可持续节奏。 Rationale:C is correct. A flat burn-down for 5 of 10 sprint days is a critical warning signal: either no work is completing (serious blocker) or the board/chart is not being updated. The Scrum Master must investigate and act immediately. The daily standup should surface blockers, but a flat line visible at mid-sprint demands urgent facilitator action. Normalising it (D) ignores a clear distress signal. Chart updating (A) is secondary to checking actual work completion. Overtime (B) violates sustainable pace without understanding the cause.