题目
项目收尾时项目经理核对成本:最终 AC 为 52 万美元,BAC 为 50 万美元。发起人问为何超支。最准确的解释是什么?
During project closure, the project manager is reconciling project costs. The final AC is $520,000 against a BAC of $500,000. The sponsor asks why the project exceeded budget. What is the most accurate explanation?
选项
- A.The overrun is within an acceptable 4% tolerance and does not need explanation.
- B.The project exceeded budget: actual costs exceeded the Budget at Completion. A root cause analysis of where and why costs exceeded plan should be presented to the sponsor.
- C.The budget estimate was inaccurate from the beginning, the team should not be blamed.
- D.The project was over budget because CPI was below 1.0 throughout execution.
解析
解析:B 正确。发起人应当得到诚实、事实性的解释:AC 超过 BAC。根因分析可判断超支源于估算错误、范围变更、风险发生还是效率低下——不同原因对应未来项目的不同纠正措施。CPI 历史(D)是有力佐证但不是完整解释;“可接受容差”(A)并非通用标准,不应默认存在;把责任推给估算不准(C)是回避担责。
Rationale:B is correct. The sponsor deserves an honest, factual explanation: AC exceeded BAC. A root cause analysis identifies whether the overrun resulted from estimation errors, scope changes, risk materialisation or inefficiency. Each requiring different corrective actions on future projects. CPI history (D) is relevant supporting data but not the full explanation. "Acceptable tolerance" (A) is not a universal standard and should not be assumed. Deflecting to estimate inaccuracy (C) avoids accountability.