职业道德与合规 中等 Business Environment 商业环境域 题号 PMP202611-334

题目

项目经理在某国工作,当地“便利费”(为加速常规政府审批而给的小额贿赂)是普遍做法。一名成员建议支付该费用以避免 4 周延误。项目经理应该怎么做?
A project manager is working in a country where facilitation payments (small bribes to expedite routine government approvals) are common practice. A team member suggests making such a payment to avoid a 4-week delay. What should the project manager do?

选项

  1. A.Request guidance from the local team about whether the payment is truly necessary.
  2. B.Make the payment. It is a standard local business practice and the delay is significant.
  3. C.Refuse the payment regardless of local practice: PMI's Code of Ethics prohibits bribery and corrupt practices. Report the situation to the sponsor and legal team and pursue legitimate alternatives.
  4. D.Ask the team member to make the payment independently so the PM is not directly involved.
正确答案:C

解析

解析:C 正确。PMI 道德准则明确禁止贿赂与腐败行为,不因当地惯例而豁免。“入乡随俗”不能为违反道德的行为开脱。项目经理必须拒绝并走正当升级路径。直接支付(B)或借他人之手(D)都违反准则——间接参与并不能免责;只向本地团队咨询(A)不如明确拒绝并通过正规渠道报告完整。 Rationale:C is correct. PMI's Code of Ethics explicitly prohibits bribery and corrupt practices regardless of local norms. "When in Rome" is not an acceptable justification for ethics violations. The PM must refuse and pursue legitimate escalation paths. Making the payment directly (B) or through a third party (D) both violate the Code: indirect involvement doesn't absolve the PM. Seeking local guidance (A) is less complete than refusing and reporting through proper channels.