领导力风格与团队激励 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-325

题目

项目经理被要求带领一个团队,该团队反映上一任 Scrum Master“管得太死”“所有决定都由他做”。项目经理应首先采用哪种领导风格?
A project manager is asked to manage a team that previously reported that their last Scrum Master was "too controlling" and "made all the decisions." What leadership style should the project manager adopt first?

选项

  1. A.Assess the team over two sprints before adopting any leadership style.
  2. B.Laissez-faire: step back completely and let the team self-manage without guidance.
  3. C.Directive: establish clear authority early to prevent the dysfunction that likely developed under the previous manager.
  4. D.Servant leadership: explicitly empower the team to make decisions, ask coaching questions rather than giving answers, and gradually build trust by demonstrating respect for their autonomy.
正确答案:D

解析

解析:D 正确。经历过强控制领导的团队需要重建对领导关系的信任。仆人式领导明确把决策交还团队,以教练代替指令,正对上一任留下的创伤。指令式(C)会印证团队的担忧;放任式(B)等于撒手不管;先观察两冲刺(A)则推迟了团队从第一天就需要的关系修复。 Rationale:D is correct. A team that experienced controlling leadership needs to rebuild trust in leader-team relationships. Servant leadership, explicitly handing decisions back to the team, coaching rather than directing, directly addresses the wound left by the previous approach. Directive leadership (C) would confirm the team's fears. Laissez-faire (B) abandons the team without support. Observation before adoption (A) delays the healing the team needs from day one.