管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-324

题目

某团队成员技术出色,但经常错过截止日期,并常在团队会议上用跑题讨论打断议程。此前非正式反馈无效。项目经理下一步应该怎么做?
A project manager has a team member who is technically brilliant but regularly misses deadlines and disrupts team meetings with tangential discussions. Previous informal feedback has had no effect. What should the project manager do next?

选项

  1. A.Escalate to the team member's functional manager and involve HR to establish a formal performance improvement process with clear expectations and consequences.
  2. B.Ignore the disruptions and only address the deadline issue since that directly impacts the project.
  3. C.Remove the team member from the project since informal feedback has failed.
  4. D.Assign a team member to monitor the individual and report back on their behaviour.
正确答案:A

解析

解析:A 正确。非正式反馈无效后,下一步应走正式流程:邀请职能经理与 HR 参与,形成书面的期望与后果。这是恰当的升级路径。直接调离(C)跳过了正式改进流程;让同事监视(D)制造监控氛围、破坏信任;只挑一个问题处理(B)会让该行为继续影响团队运作。 Rationale:A is correct. When informal feedback fails, the next step is a formal process: involving the functional manager and HR with documented expectations and consequences. This is the appropriate escalation path. Removal (C) skips the formal improvement process. Peer monitoring (D) creates surveillance dynamics and trust issues. Selectively ignoring disruptions (B) allows the behaviour to continue affecting team functioning.