敏捷估算与故事点 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-323

题目

某敏捷团队每个冲刺都有未完成事项被顺延,且团队总有合理解释。该模式持续四个冲刺后,最可能的根本原因是什么?
An agile team is consistently finishing sprints with incomplete items carried over. The team always has a good explanation. After four sprints of this pattern, what is the most likely root cause?

选项

  1. A.The team is not working hard enough and needs to increase their hours.
  2. B.The sprint length is too short for the complexity of the work.
  3. C.The team is consistently over-committing during sprint planning: velocity-based capacity planning is not being applied correctly.
  4. D.The Product Owner is adding too many stories mid-sprint.
正确答案:C

解析

解析:C 正确。四个冲刺持续出现顺延,且理由各不相同,几乎总是指向计划阶段的超额承诺——团队按速率算产能的方式不对,总是承诺超过历史实际吞吐量的点数。解决办法是用真实历史速率设定冲刺产能。靠加时(A)违反可持续节奏;冲刺周期(B)是次要因素;产品负责人中途加故事(D)会在团队的解释中体现出来。 Rationale:C is correct. A consistent pattern of carryover across four sprints, despite varying reasons, almost always points to over-commitment at planning. The team's velocity-based capacity calculation is incorrect, likely by consistently committing to more points than their proven throughput. The fix is to use actual historical velocity to set sprint capacity. More hours (A) violates sustainable pace. Sprint length (B) is a secondary consideration. Mid-sprint PO additions (D) would be visible in the team's explanations.