团队发展阶段 · PMP 练习题解析

首页 › People 人域 › 资源管理 › 团队发展阶段 › PMP202611-321
资源管理 中等 People 人域 题号 PMP202611-321

题目

某 Scrum 团队已合作 12 个冲刺,表现良好。组织决定增加两名开发人员以提升产能。最可能的短期影响是什么,Scrum Master 应如何准备?
A Scrum team has been together for 12 sprints and is performing well. The organisation decides to add two new developers to increase capacity. What is the most likely short-term impact and how should the Scrum Master prepare?

选项

  1. A.Velocity will immediately increase by the proportion of new members added.
  2. B.There will be no impact since the team is already high-performing.
  3. C.The new members should shadow the existing team for two sprints before contributing to the sprint backlog.
  4. D.Velocity will likely decrease temporarily as the team re-forms, norms adjust and new members onboard. The Scrum Master should plan for a transition period and reset velocity expectations.
正确答案:D

解析

解析:D 正确。布鲁克斯定律指出“向已延期的软件项目增人只会更晚”。即便项目进展正常,增员也会重置团队动力,团队回到形成期/震荡期。知识传递、规范重建与融合都需要时间。Scrum Master 应设定现实预期,按速率下降 2~3 个冲刺后再回升来规划。速率立即提升(A)不现实;高效团队也无法免疫人员变动冲击(B);只观察不参与(C)无谓地推迟了贡献。 Rationale:D is correct. Brooks' Law: "Adding manpower to a late software project makes it later." Even for on-track projects, adding members resets team dynamics, the group returns to the forming/storming stages. Knowledge transfer, norming and integration take time. The Scrum Master should set realistic expectations and plan for a 2–3 sprint reduction in velocity before improvement. Immediate velocity increase (A) is unrealistic. High performance doesn't immunise against team change disruption (B). Passive shadowing (C) delays contribution unnecessarily.