题目
某 Scrum 团队已合作 12 个冲刺,表现良好。组织决定增加两名开发人员以提升产能。最可能的短期影响是什么,Scrum Master 应如何准备?
A Scrum team has been together for 12 sprints and is performing well. The organisation decides to add two new developers to increase capacity. What is the most likely short-term impact and how should the Scrum Master prepare?
选项
- A.Velocity will immediately increase by the proportion of new members added.
- B.There will be no impact since the team is already high-performing.
- C.The new members should shadow the existing team for two sprints before contributing to the sprint backlog.
- D.Velocity will likely decrease temporarily as the team re-forms, norms adjust and new members onboard. The Scrum Master should plan for a transition period and reset velocity expectations.
解析
解析:D 正确。布鲁克斯定律指出“向已延期的软件项目增人只会更晚”。即便项目进展正常,增员也会重置团队动力,团队回到形成期/震荡期。知识传递、规范重建与融合都需要时间。Scrum Master 应设定现实预期,按速率下降 2~3 个冲刺后再回升来规划。速率立即提升(A)不现实;高效团队也无法免疫人员变动冲击(B);只观察不参与(C)无谓地推迟了贡献。
Rationale:D is correct. Brooks' Law: "Adding manpower to a late software project makes it later." Even for on-track projects, adding members resets team dynamics, the group returns to the forming/storming stages. Knowledge transfer, norming and integration take time. The Scrum Master should set realistic expectations and plan for a 2–3 sprint reduction in velocity before improvement. Immediate velocity increase (A) is unrealistic. High performance doesn't immunise against team change disruption (B). Passive shadowing (C) delays contribution unnecessarily.