题目
某项目 BAC 为 40 万美元。在评审点,AC = 20 万美元,EV = 18 万美元,PV = 21 万美元。完工偏差(VAC)是多少?
A project's BAC is $400,000. At the review point, AC = $200,000, EV = $180,000, PV = $210,000. What is the Variance at Completion (VAC)?
选项
- A.−$44,444
- B.−$20,000
- C.+$20,000
- D.−$44,000
解析
解析:A 正确。CPI = 180,000 ÷ 200,000 = 0.90;EAC = 400,000 ÷ 0.90 ≈ 444,444;VAC = BAC − EAC = 400,000 − 444,444 ≈ −44,444。VAC 为负表示预计将超预算约 44,444 美元。负 VAC 始终代表预计成本超支。
Rationale:A is correct. CPI = EV ÷ AC = 180,000 ÷ 200,000 = 0.90. EAC = BAC ÷ CPI = 400,000 ÷ 0.90 = $444,444. VAC = BAC − EAC = $400,000 − $444,444 = −$44,444. The negative VAC indicates the project is forecasted to exceed budget by approximately $44,444. A negative VAC always means a projected cost overrun.