题目
一位此前支持项目的相关方如今在指导委员会上公开反对。项目经理很意外,因为此前没有任何不满迹象。最可能的原因与最佳应对是什么?
A stakeholder who previously supported the project is now openly opposing it in steering committee meetings. The project manager is surprised as there was no prior indication of dissatisfaction. What is the most likely cause and best response?
选项
- A.Ask the sponsor to intervene and instruct the stakeholder to support the project.
- B.The stakeholder has been influenced by competitors: report this to the sponsor.
- C.Present a stronger business case at the next steering committee to win back support.
- D.The stakeholder's engagement level was not monitored adequately. Meet with them privately to understand their concerns, re-engage them, and update the stakeholder engagement plan.
解析
解析:D 正确。突然反对通常说明相关方监测失效:参与度跟踪不足,未能发现其顾虑。第一步永远是私下沟通弄清根因,并更新相关方参与计划以防再发。臆测外部影响(B)无依据;只讲商业论证(C)是治标不治本;借发起人施压(A)只得到表面服从,没有真正认同。
Rationale:D is correct. A surprise opposition usually signals a failure in stakeholder monitoring: their concerns went undetected because engagement tracking was insufficient. The first step is always a private conversation to understand the root cause. Updating the stakeholder engagement plan prevents recurrence. Assuming external influence (B) is speculative. A business case presentation (C) addresses the symptom without understanding the cause. Forcing support through the sponsor (A) creates compliance without genuine buy-in.
同考点练习题
-
PMP202603-001 · 答案 D
-
PMP202603-002 · 答案 B
-
PMP202603-005 · 答案 D
-
PMP202611-002 · 答案 A,B
-
PMP202611-024 · 答案 B
-
PMP202611-147 · 答案 B
-
PMP202611-151 · 答案 B
-
PMP202611-250 · 答案 B