团队建设与团队章程 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-286

题目

一个新组建的敏捷团队正处于“震荡期”:分歧频繁、凝聚力低。Scrum Master 担心第一个冲刺。最有效的做法是什么?
A newly formed agile team is in the "storming" phase: disagreements are frequent and team cohesion is low. The Scrum Master is concerned about the first sprint. What is the most effective action?

选项

  1. A.Replace conflicting team members with more collaborative individuals.
  2. B.Facilitate the creation of a team working agreement, model effective conflict resolution techniques, and allow the team to navigate healthy disagreements with coaching support.
  3. C.Intervene in every disagreement to prevent conflict from affecting the sprint.
  4. D.Delay the first sprint until the team reaches the "norming" phase.
正确答案:B

解析

解析:B 正确。塔克曼阶段(组建→震荡→规范→高效)是正常的团队发展规律。Scrum Master 的职责是促成团队健康穿越震荡期,而非消灭冲突。工作协议提供共享规范,冲突中的辅导能培养能力。事事介入(C)让团队学不会解决冲突;换人(A)等于把团队打回组建期;推迟冲刺(D)不现实。 Rationale:B is correct. Tuckman's stages (Forming → Storming → Norming → Performing) are a normal team development pattern. The Scrum Master's role is to facilitate healthy passage through storming, not eliminate it. A working agreement provides shared norms; coaching during conflicts builds capability. Intervening in every disagreement (C) prevents the team from developing conflict resolution skills. Replacing members (A) resets the team to forming. Delaying (D) is impractical.