领导力风格与团队激励 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-280

题目

某敏捷团队已能自组织,但遇到技术问题仍不断向 Scrum Master 索取方向。Scrum Master 恰好具备回答的技术专长。最佳做法是什么?
An agile team is self-organising but keeps asking the Scrum Master for direction on how to solve technical problems. The Scrum Master has the technical expertise to answer. What is the best approach?

选项

  1. A.Use coaching questions to guide the team toward their own solutions, gradually reducing dependence on the Scrum Master for technical decisions.
  2. B.Refer all technical questions to a technical architect outside the team.
  3. C.Answer the technical questions directly: using available expertise speeds up delivery.
  4. D.Tell the team they must solve technical problems themselves as the Scrum Master does not make technical decisions.
正确答案:A

解析

解析:A 正确。Scrum Master 的目标是建设团队能力与自组织。即使知道答案,直接给出也会制造依赖。教练式提问(“你们考虑过哪些方案?”“你认为权衡点在哪?”)能持续提升团队的解题能力。直接回答(C)看似高效,实则削弱自组织;转给外部(B)增加时延;生硬拒绝(D)无益且显得敷衍。 Rationale:A is correct. The Scrum Master builds team capability and self-organisation. Even when the SM has the answer, providing it directly creates dependency. Coaching questions ("What options have you considered?", "What do you think the trade-offs are?") build the team's problem-solving capability over time. Answering directly (C) feels efficient but undermines self-organisation. Referring outside (B) adds latency. A blunt refusal (D) is unhelpful and may feel dismissive.