题目
项目经理发现一名原本积极的成员变得沉默寡言、不再参与会议,看起来压力很大。项目正要进入最关键阶段。项目经理首先应该怎么做?
A project manager notices that a team member who was previously enthusiastic has become withdrawn, stopped participating in meetings, and appears stressed. The project is entering its most critical phase. What should the project manager do first?
选项
- A.Mention the change in behaviour during the team meeting to raise awareness.
- B.Have a private, empathetic one-on-one conversation to check in on their wellbeing and understand what is affecting them.
- C.Increase workload monitoring to ensure the team member is meeting their commitments.
- D.Reassign the team member's critical tasks to protect the project during this phase.
解析
解析:B 正确。这些表现提示倦怠、个人压力或工作困扰,第一步都应是私下、有同理心的沟通。PMI 一贯强调成员福祉与仆人式领导。转交任务(D)在未弄清问题前就跳到方案;加强监控(C)在本已紧张的情境下加压;公开提及(A)侵犯隐私与尊严。
Rationale:B is correct. The visible signs suggest burnout, personal stress or work-related issues: all requiring an empathetic private conversation as the first step. PMI consistently emphasises team member wellbeing and servant leadership. Reassigning tasks (D) jumps to a solution before understanding the problem. Increased monitoring (C) creates pressure in an already stressed situation. Raising it publicly (A) violates the team member's privacy and dignity.