题目
项目经理向指导委员会汇报状态。项目已落后进度,但项目经理相信团队能够追回。报告应如何呈现?
A project manager is presenting a status report to the steering committee. The project is behind schedule but the project manager believes the team will recover. What should the report show?
选项
- A.Wait until the recovery is confirmed before reporting the delay to avoid unnecessary concern.
- B.Report the project as on track since the PM believes recovery is possible.
- C.Report the delay but omit the recovery plan to avoid raising false hope.
- D.Accurately report the schedule variance, present the recovery plan with realistic timelines, and give the committee the information they need to make informed decisions.
解析
解析:D 正确。PMI 道德准则与 PMBOK 都要求准确、透明的汇报。相关方有权知道真实状态。项目经理应如实报告延误,同时给出恢复计划,既交代背景也展现主动管理。报成按计划(B)是不诚实;只报延误不给计划(C)不完整;等追回再报(A)剥夺了相关方所需信息。
Rationale:D is correct. PMI's Code of Ethics and PMBOK both require accurate, transparent reporting. Stakeholders are entitled to true project status. The project manager should report the delay honestly while also providing the recovery plan: giving context and showing proactive management. Reporting as on track (B) is dishonest. Reporting delay without a plan (C) is incomplete. Waiting for recovery (A) deprives stakeholders of information they need.