三重约束与知情决策 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-272

题目

项目经理被要求 6 个月交付一个团队估算需 9 个月的项目,发起人坚持截止日期不可变。项目经理应该怎么做?
A project manager has been asked to deliver a project in 6 months that the team estimates will take 9 months. The sponsor insists the deadline is fixed. What should the project manager do?

选项

  1. A.Accept the 6-month deadline and quietly plan for a 9-month delivery, hoping the sponsor will extend later.
  2. B.Tell the sponsor the project cannot be done and refuse to take it on.
  3. C.Present the sponsor with options: increase resources, reduce scope, accept the 9-month timeline, or accept higher risk, and document the agreed approach.
  4. D.Commit to the 6-month deadline and plan to work the team overtime to meet it.
正确答案:C

解析

解析:C 正确。项目经理的职责是把选项讲清楚,让发起人在知情下决策。三重约束(范围、进度、成本)意味着一项改变必然牵动其他项,可选路径包括赶工(加资源)、快速跟进、削减范围或顺延工期。硬扛不现实期限(D)等于给团队埋下失败;直接拒绝(B)无助于事;暗中按 9 个月排计划(A)是欺骗,违反 PMI 道德准则。 Rationale:C is correct. The project manager's role is to present options clearly and let the sponsor make an informed decision. The triple constraint (scope, schedule, cost) means changing one requires adjusting the others. Options include crashing (more resources), fast-tracking, scope reduction or schedule extension. Committing to an unrealistic deadline (D) sets the team up for failure. Refusing (B) is unhelpful. Hidden planning (A) is deceptive and a PMI Code of Ethics violation.