虚拟与分布式团队协作 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-271

题目

一个分布式敏捷团队横跨三个时区。由于关键讨论都安排在对某一地点更有利的重叠时段,其他时区的成员感到被排除在决策之外。Scrum Master 应该怎么做?
A distributed agile team spans three time zones. Team members in different zones feel excluded from decision-making because key discussions happen during overlapping hours that favour one location. What should the Scrum Master do?

选项

  1. A.Ask remote team members to adjust their working hours to overlap with the majority.
  2. B.Designate one time zone as the official team time zone and ask all members to adjust.
  3. C.Split the team into location-based sub-teams that work independently and sync weekly.
  4. D.Rotate meeting times across time zones so the inconvenience is shared equally, and record all key decisions for asynchronous review.
正确答案:D

解析

解析:D 正确。轮换会议时间让不便公平分摊,并以行动表示对所有成员的尊重,这是仆人式领导的核心。记录决策可保证异步参与。固定一个时区(B)会长期牺牲其他人;拆分子团队(C)破坏团队一体性并增加协调成本;总让远程成员迁就(A)会引发怨气与倦怠。 Rationale:D is correct. Rotating meeting times distributes inconvenience fairly and signals respect for all team members equally, a core servant leadership principle. Recording decisions ensures asynchronous inclusion. Designating one time zone (B) permanently disadvantages others. Splitting into sub-teams (C) breaks the unified team dynamic and increases coordination overhead. Asking remote members to always adjust (A) creates resentment and burnout.