商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-268

题目

某敏捷团队正在增量交付产品。业务发起人问:“我怎样才能知道每个冲刺都在产生价值?”展示价值的最佳方式是什么?
An agile team is delivering a product incrementally. The business sponsor asks: "How do I know we're getting value from each sprint?" What is the best way to demonstrate value?

选项

  1. A.Provide a written summary of completed user stories with acceptance criteria met.
  2. B.Provide detailed sprint velocity charts and story point completion reports.
  3. C.Show the sponsor working software at each sprint review and connect delivered features to measurable business outcomes.
  4. D.Share the team's burn-down chart to demonstrate consistent progress through the backlog.
正确答案:C

解析

解析:C 正确。敏捷宣言强调可运行软件高于完备文档。业务价值要通过可运行软件及其带来的可衡量成果来体现,而不是靠内部度量。速率图(B)与燃尽图(D)是团队内部工具,说不清业务价值;书面总结(A)有用,但不如现场演示可运行功能。 Rationale:C is correct. The Agile Manifesto prioritises working software over comprehensive documentation. Business value is demonstrated through working software that delivers measurable outcomes, not internal metrics. Velocity charts (B) and burn-down charts (D) are team-internal tools that don't speak the language of business value. Written summaries (A) are useful but secondary to a live demonstration of working functionality.