项目经理被要求确保项目符合一项在项目规划完成之后才生效的新数据隐私法规。合规要求将带来额外成本与延误。项目经理应该怎么做?
A project manager is asked to ensure the project complies with a new data privacy regulation that came into effect after project planning was completed. The compliance requirements will add cost and delay. What should the project manager do?

选项

  1. A.Ignore the regulation since it was not in scope when the project was planned.
  2. B.Ask the legal team to determine if the regulation applies to the project.
  3. C.Implement the compliance requirements immediately without a change request to avoid regulatory penalties.
  4. D.Assess the compliance requirements, raise a change request for the additional scope, cost and schedule impact, and obtain proper approvals before proceeding.
正确答案:D

解析

解析:D 正确。法规合规是强制要求,不能忽视;但正确做法是提交正式变更请求,记录对范围、进度和成本的影响,让相关方在知情下决策。无视法规(A)带来法律风险;无变更请求直接实施(C)绕过治理,造成基准失控。法务意见(B)可能有帮助,但项目经理还必须管理流程影响,因此该选项作为单独答案不完整。 Rationale:D is correct. Regulatory compliance is mandatory. It cannot be ignored. However, the correct process is to raise a formal change request that documents the impact on scope, schedule and cost so that stakeholders can make informed decisions. Ignoring the regulation (A) creates legal risk. Implementing without a change request (C) bypasses governance and creates an uncontrolled baseline change. While legal input (B) may be helpful, the PM must also manage the process impact: making it incomplete as a standalone answer.