资源管理 中等 People 人域 题号 PMP202611-252

题目

项目经理发现一位掌握关键技能的资深成员明显投入度下降:参加会议但不发言,工作质量低于其平时水准。项目正处于关键阶段。项目经理首先应该怎么做?
A project manager notices that a senior team member with critical skills appears disengaged: attending meetings without contributing and producing work below their usual standard. The project is at a critical juncture. What should the project manager do first?

选项

  1. A.Document the performance decline and report it to HR for guidance.
  2. B.Reassign the team member's critical tasks to other team members to protect the project schedule.
  3. C.Have a private, empathetic conversation with the team member to understand what is affecting their engagement and explore how to support them.
  4. D.Place the team member on a performance improvement plan to formally address the quality decline.
正确答案:C

解析

解析:C 正确。PMI 一贯主张以有同理心的直接沟通作为处理团队成员问题的第一步。投入度下降往往有可识别的原因——个人困难、角色不清、感到不被重视——这些都可以化解。绩效改进计划(D)在调查前就升级;转交任务(B)回避问题且丢失关键技能;直接找 HR(A)在未沟通前属过早。 Rationale:C is correct. PMI consistently favours empathetic, direct communication as the first response to team member issues. Disengagement often has an identifiable cause, personal challenges, unclear role, feeling undervalued, that can be addressed. A performance plan (D) escalates before investigating. Reassigning tasks (B) removes the issue without understanding it and loses critical skills. Going to HR (A) is premature without a direct conversation first.