一名新成员在冲刺中途加入,随即开始质疑团队既有规范,认为当前做法效率低下。其他成员逐渐感到沮丧。Scrum Master 应该怎么做?
A new team member joins mid-sprint and immediately begins challenging established team norms, arguing that the current approach is inefficient. Other team members are becoming frustrated. What should the Scrum Master do?
选项
- A.Ask the Product Owner to talk to the new team member about respecting team norms.
- B.Acknowledge the new member's perspective, protect the current sprint from disruption, and channel their improvement ideas into the next retrospective.
- C.Tell the new team member to observe quietly during the first sprint before suggesting changes.
- D.Hold a team vote on whether to adopt the new member's suggested approach immediately.
解析
解析:B 正确。Scrum Master 需要在保护当前冲刺(中途变动会降低速率与专注度)与真正重视改进建议之间取得平衡。把建议引导到回顾会,是敏捷中推动流程改变的正确机制。简单让新人闭嘴(C)会打击改进文化;冲刺中途投票(D)干扰流动;交给产品负责人(A)错置了 Scrum Master 的引导职责。
Rationale:B is correct. The Scrum Master balances protecting the sprint (mid-sprint disruption reduces velocity and focus) with genuinely valuing improvement ideas. Channelling suggestions into the retrospective is the correct agile mechanism for process change. Simply silencing the new member (C) discourages improvement culture. Voting mid-sprint (D) disrupts flow. Delegating to the PO (A) misplaces the Scrum Master's facilitation responsibility.