题目
项目经理带领一个混合型团队:三名成员按敏捷冲刺工作,五名成员按预测型计划推进。两个小组各自产出相互冲突的状态报告,相关方感到困惑。项目经理应该怎么做?
A project manager is leading a hybrid team. Three members work in agile sprints while five follow a predictive plan. The two subgroups are creating separate status updates that conflict. Stakeholders are confused. What should the project manager do?
选项
- A.Let both subgroups continue reporting separately and schedule a weekly meeting to reconcile differences.
- B.Ask stakeholders to review both reports and draw their own conclusions.
- C.Create an integrated communication plan that translates both subgroup outputs into a unified stakeholder-facing status report.
- D.Ask the agile subgroup to adopt predictive reporting so all reporting is consistent.
解析
解析:C 正确。混合环境下,项目经理的职责是衔接两种交付方式,而不是强迫一种方式服从另一种。整合的沟通计划既满足相关方需要,又不破坏各团队的工作节奏。强迫敏捷团队用预测型汇报(D)会伤害其节奏;继续分开汇报(A)让混乱延续;让相关方自己去核对(B)是把沟通责任推给相关方。
Rationale:C is correct. In a hybrid environment the PM's role is to bridge the two delivery approaches, not force one to conform to the other. A unified communication plan satisfies stakeholder needs without disrupting each team's working method. Forcing agile to use predictive reporting (D) damages the agile team's cadence. Continuing separate reports (A) maintains the confusion. Asking stakeholders to reconcile (B) offloads the PM's communication responsibility.
同考点练习题
-
PMP202611-297 · 答案 D
-
PMP202611-455 · 答案 B
-
PMP202611-537 · 答案 D