整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-247

题目

项目经理发现两名团队成员绕过正式变更控制流程,直接在生产环境实施了小改动。这些改动目前尚未引发问题。项目经理首先应该怎么做?
A project manager discovers that two team members have been bypassing the formal change control process by implementing small changes directly in production. The changes have not caused issues yet. What should the project manager do first?

选项

  1. A.Meet with the team members to understand why they bypassed the process, explain the importance of change control, and reinforce the correct procedure.
  2. B.Ignore the issue since no harm has been done yet and monitor for future incidents.
  3. C.Document the unauthorised changes and report them to the sponsor.
  4. D.Raise a formal disciplinary action against both team members immediately.
正确答案:A

解析

解析:A 正确。PMI 一贯主张先直接、建设性地处理问题,再考虑上报。与成员面谈可以找到根因、纠正行为并维护团队关系。首次违规且未造成影响就处分(D)过重;只记录上报(C)跳过了直接沟通;放任不管(B)会让风险持续。 Rationale:A is correct. PMI's preferred approach is always to address issues directly and constructively before escalating. Meeting with the team members addresses the root cause, reinforces correct behaviour and maintains team relationships. Immediate disciplinary action (D) is disproportionate for a first offence with no impact. Simply documenting and reporting (C) skips the direct conversation. Ignoring it (B) allows the risk to continue.

同考点练习题