题目
在冲刺计划中,某成员持续低估自己的任务工作量,导致冲刺目标未能达成。在回顾会上被提及时,该成员表现得防御性很强。最佳做法是什么?
During sprint planning, a team member consistently underestimates their tasks, causing sprint goals to be missed. The team member becomes defensive when this is raised in retrospectives. What is the best approach?
选项
- A.Publicly review the team member's estimates during sprint planning to create accountability pressure.
- B.Assign the team member fewer tasks each sprint so their estimates cannot derail the sprint goal.
- C.Have a private coaching conversation with the team member to explore the root cause of the underestimation pattern and co-create a plan to improve accuracy.
- D.Document the pattern and raise it formally with the team member's line manager.
解析
解析:C 正确。仆人式领导强调个体辅导与心理安全。私下沟通可以判断问题出在技能(需培训)、意愿(需问责)还是方法(需改进估算技术,如扑克估算)。减少任务(B)回避根因;公开点评(A)破坏心理安全,会加剧防御;直接上报(D)跳过了辅导环节。
Rationale:C is correct. Servant leadership prioritises individual coaching and psychological safety. A private conversation lets the Scrum Master understand whether the issue is skill (needs training), will (needs accountability) or process (needs technique improvement like planning poker). Limiting tasks (B) avoids the root cause. Public scrutiny (A) violates psychological safety and will worsen defensiveness. Formal escalation (D) skips the coaching step entirely.