管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-230

题目

两名成员之间的冲突已酝酿数周,如今开始影响交付物,但两人都坚称一切正常。你应该怎么做?
A conflict between two team members has been simmering for weeks and is now affecting deliverables, but both insist everything is fine. What should you do?

选项

  1. A.Address the conflict openly, as it is now affecting the work.
  2. B.Continue to respect their statement that everything is fine.
  3. C.Separate them permanently so they never interact.
  4. D.Decide who is right and instruct them to comply.
正确答案:A

解析

解析:冲突一旦影响交付物,项目经理就必须公开处理,而不能接受“没事”的说法。采信表面说辞会无视明显的影响证据;永久隔离回避了解决;判定胜负只是强加结果而未解决根因。 Rationale:Once a conflict affects deliverables, the PM must address it openly rather than accept the denial. Taking their word at face value ignores clear evidence of impact; permanent separation avoids resolution; picking a winner forces an outcome without resolving the cause.