管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-231

题目

一位相关方坚持要求某功能,而团队坚信该功能对用户不安全。项目经理应如何处理这一冲突?
A stakeholder demands a feature that the team strongly believes is unsafe for users. How should the project manager handle the conflict?

选项

  1. A.Side with the stakeholder since they hold the requirement.
  2. B.Side with the team and refuse the feature outright.
  3. C.Build the feature and add a disclaimer to limit liability.
  4. D.Bring the stakeholder and team together to weigh the safety concerns and find an acceptable path.
正确答案:D

解析

解析:让双方共同评估安全并寻找可行路径,既尊重相关方,也正视真实的安全隐患。一味顺从相关方等于无视风险;靠免责声明推出不安全功能在伦理与专业上都不可接受。 Rationale:Convening both sides to weigh safety and find an acceptable path respects the stakeholder while honouring a genuine safety concern. Automatically siding with the stakeholder ignores real risk; shipping something unsafe with a disclaimer is ethically and professionally wrong.