一名成员技术出色,但对初级同事态度轻慢,后者已开始消极疏离。项目经理首先应该做什么?
A team member is technically excellent but dismissive toward junior colleagues, who are starting to disengage. What should the project manager do FIRST?
选项
- A.Tolerate it because the member's output is valuable.
- B.Give the member direct, specific feedback about the impact of their behaviour.
- C.Move the junior members away from that person.
- D.Raise the behaviour anonymously in a team meeting.
解析
解析:直接且具体的反馈既给对方明确的改进机会,也保护了初级成员,体现情商与责任担当。容忍等于牺牲整个团队;调走初级成员则回避了真正的问题。
Rationale:Direct, specific feedback gives the person a clear chance to change and protects the juniors, reflecting emotional intelligence and accountability. Tolerating it sacrifices the wider team; moving the juniors avoids the real issue.