矩阵型组织与资源协商 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-226

题目

一位资深相关方屡次越过你,直接向团队成员下达指令,造成混乱。最好的做法是什么?
A senior stakeholder repeatedly bypasses you and gives instructions directly to your team members, creating confusion. What is the BEST approach?

选项

  1. A.Speak with the stakeholder to align on how requests should flow, while keeping the relationship positive.
  2. B.Tell your team to ignore any instruction that does not come from you.
  3. C.Escalate the behaviour to the sponsor as interference.
  4. D.Let it continue to avoid friction with a senior stakeholder.
正确答案:A

解析

解析:直接与相关方就可行的流程达成一致,既保护团队又维系重要关系,符合“参与优先于对抗”的思路。让团队无视对方会引发正面冲突;先上报则跳过了直接沟通。 Rationale:Aligning directly with the stakeholder on a workable process protects the team while preserving an important relationship, which fits the emphasis on engagement over confrontation. Telling the team to ignore them creates open conflict; escalating first skips the direct conversation.