冲刺期间,两位资深开发人员当着全团队的面公开争论技术设计,语气已开始针对个人。作为项目经理,最好的第一步是什么?
During a sprint, two senior developers openly disagree about the technical design in front of the whole team, and the tone is getting personal. As the project manager, what is the BEST first action?
选项
- A.Decide the design yourself so the team can move on.
- B.Bring the two together to surface the underlying interests and facilitate them toward a shared solution.
- C.Ask the product owner to pick the winning design.
- D.Let them keep debating since healthy conflict is good.
解析
解析:合作解决问题能触及根本利益,产生最持久的成果,是首选的冲突处理方式。自己拍板浪费了专家的价值;推给产品负责人则把技术决策放错了位置;放任继续会让任务冲突演变为关系冲突。
Rationale:Collaborating addresses the root interests and produces the most durable outcome, which is the preferred conflict mode. Deciding yourself wastes their expertise; pushing it to the product owner mislocates a technical decision; letting it continue turns a task conflict into a relationship conflict.