一支新组建的敏捷团队氛围友好,却回避艰难对话,问题往往被隐藏到演变成障碍才暴露。哪项行动最有助于团队成熟?
A newly formed agile team is friendly but avoids hard conversations, so problems stay hidden until they become blockers. Which action best helps the team mature?
选项
- A.Assign one person as the official problem reporter.
- B.Facilitate a team working agreement that makes it safe and expected to raise problems early.
- C.Add a penalty for anyone who surprises the team with a late blocker.
- D.Escalate every hidden problem to the sponsor as it appears.
解析
解析:与团队共建工作协议能建立心理安全与共同规范,这正是组建期或震荡期团队学会暴露问题的方式。指定专人会让提问题变成别人的事;惩罚则会把问题逼到更隐蔽处。
Rationale:A working agreement built with the team creates psychological safety and shared norms, which is how a forming or storming team learns to surface issues. Naming one reporter makes it someone else's job; penalties drive problems underground.