你的项目属于一个更大的项目集。一项对你项目有利的决策会损害同一项目集中的另一个项目。你应该怎么做?
Your project sits within a larger program. A decision that benefits your project would harm another project in the same program. What should you do?
选项
- A.Make the decision that is best for your own project.
- B.Let the other project's manager handle the fallout.
- C.Raise it to the program level so the overall program benefit can be optimised.
- D.Proceed and hope the program impact is small.
解析
解析:提交项目集层面才能优化整体,体现“项目集优先于单个项目”的系统观。只优化自己的项目可能损害更大目标。
Rationale:Escalating to the program level optimises the whole, reflecting the systems view that the program outranks any single project. Optimising only your project can damage the larger objective.