项目组合与项目集管理 · PMP 练习题解析

商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-219

题目

你的项目属于一个更大的项目集。一项对你项目有利的决策会损害同一项目集中的另一个项目。你应该怎么做?
Your project sits within a larger program. A decision that benefits your project would harm another project in the same program. What should you do?

选项

  1. A.Make the decision that is best for your own project.
  2. B.Let the other project's manager handle the fallout.
  3. C.Raise it to the program level so the overall program benefit can be optimised.
  4. D.Proceed and hope the program impact is small.
正确答案:C

解析

解析:提交项目集层面才能优化整体,体现“项目集优先于单个项目”的系统观。只优化自己的项目可能损害更大目标。 Rationale:Escalating to the program level optimises the whole, reflecting the systems view that the program outranks any single project. Optimising only your project can damage the larger objective.

同考点练习题