商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-216

题目

项目必须遵循组织治理框架,包括阶段关口。发起人要求你跳过某个关口以节省时间。你应该怎么做?
A project must follow the organisation's governance framework, including stage gates. A sponsor asks you to skip a gate to save time. What should you do?

选项

  1. A.Skip the gate as the sponsor requested.
  2. B.Skip the gate but document that the sponsor told you to.
  3. C.Refuse and report the sponsor to senior leadership immediately.
  4. D.Explain the purpose of the gate and follow the governance process, escalating if needed.
正确答案:D

解析

解析:坚持治理并解释其目的,既能保护组织,也是专业做法。跳过关口即便留痕也绕过了控制;立刻举报则跳过了通常能解决问题的建设性沟通。 Rationale:Upholding governance while explaining its purpose protects the organisation and is the professional response. Skipping it, even with a note, still bypasses control; immediately reporting the sponsor skips the constructive conversation that usually resolves this.