一项新法规在项目进行中生效,影响项目的合规义务。项目经理首先应该做什么?
A new regulation takes effect that affects your project's compliance obligations mid-flight. What should the project manager do FIRST?
选项
- A.Ignore it until the project is finished.
- B.Assess the impact on the project and incorporate the new requirements through change control.
- C.Stop the project until the regulation is fully understood.
- D.Assume the existing plan already covers it.
解析
解析:评估影响并经变更控制纳入新合规要求,才能让项目既合法又受控。无视法规会带来法律风险;全面停工通常属于反应过度。
Rationale:Assessing impact and bringing new compliance requirements through change control keeps the project lawful and controlled. Ignoring a regulation invites legal exposure; halting everything is usually disproportionate.