题目
交付进行到一半,市场发生变化,项目预期实现的商业效益如今很可能落空。最好的做法是什么?
Midway through delivery, the market shifts and the project's expected business benefits are now unlikely to materialise. What is the BEST action?
选项
- A.Raise it with the sponsor and steering group to reassess the business case.
- B.Continue to completion since the project was approved.
- C.Quietly reduce scope to finish faster regardless of benefits.
- D.Cancel the project yourself to stop wasting money.
解析
解析:当效益受到威胁时,应上报重新评估商业论证,因为项目存在的意义就是交付价值。以“已获批”为由硬推,忽视了论证前提已变;自行取消则超出权限。
Rationale:When benefits are at risk you escalate to reassess the business case, because the project exists to deliver value. Pushing on because it was approved ignores that the justification has changed; cancelling unilaterally exceeds your authority.
同考点练习题
-
PMP202611-074 · 答案 C
-
PMP202611-075 · 答案 B
-
PMP202611-195 · 答案 B
-
PMP202611-196 · 答案 B
-
PMP202611-268 · 答案 C
-
PMP202611-407 · 答案 C
-
PMP202611-412 · 答案 C
-
PMP202611-461 · 答案 A