题目

你的项目正在建设新电商平台,18 个月周期已走完 6 个月。最大竞争对手发布了类似平台,并带有一项你范围之外的功能:即时次日达集成。市场总监问是否要在发布前跟进;该功能预计增加三个月工期和 60 万成本。项目经理应该怎么做?
Your project is six months into an 18-month build of a new e-commerce platform. Your largest competitor announces a similar platform with a feature not in your scope: instant same-day delivery integration. The CMO asks whether you should match it before launch; it would add an estimated three months and 600K. What should the project manager do?

选项

  1. A.Add the feature to the scope to maintain competitive parity at launch.
  2. B.Decline the request because the feature was not in the approved baseline.
  3. C.Document the competitor change in external environment monitoring, analyse the strategic impact with the sponsor and steering committee, and route the scope decision through change control.
  4. D.Defer the feature to a post-launch release to keep the original timeline.
正确答案:C

解析

解析:外部商业环境变化应遵循由项目经理主导的结构化流程:监控并记录、与合适相关方分析战略影响、再经治理程序做出决策。项目经理负责流程,而非替业务做战略决定。直接增加、直接拒绝或直接推迟,都跳过了分析。 Rationale:External business environment changes follow a structured PM-led process: monitor and document, analyse strategic impact with the right stakeholders, then route the decision through governance. The PM owns the process, not the strategic decision. Adding, refusing or deferring unilaterally all pre-empt analysis.